Page 17 - IEC Insights Nov-Dec21_WEB
P. 17

FIGURE 1

                                                                                 • Quoting a price
                                                                                 • Procuring it
                                                                                 • Staging it
                                                                                 • Prefabricating it
                                                                                 • Delivering it
                                                                                 • Installing it
                                                                                 • Testing it
                                                                                 •  Reporting on its installation progress

                                                                                 If it’s not digital, humans are left to
                                                                                 conduct each task manually, and the
                                                                                 automation you aspire to goes by
                                                                                 the wayside.

                                                                                 This is one simple example, but when
                         STEP 1:               The most profound improvement     you consider it at the scale of an entire
                                                                                 floor or building, the efficiency gains
                                               electrical contractors can make is to
                         DIGITIZE THE          have their BIM process capture this   really change the game.
                         PREFABRICATION        information and pass it along the supply
                         OF ASSEMBLIES.        chain. That is what translates to hard
                                               labor savings.                                   STEP 2: EXPAND
                                                                                                FABRICATION
            Assemblies are the core building block   The first step to digitizing prefabrications
            of electrical construction, and most   is to attribute data to an object early in   TO INCLUDE
            likely you are already prefabricating   the process.                                CONDUIT.
            wall assemblies, fixture whips and
            the like. But if you want to automate   For example, a wall assembly may
            more of that work, you can do it   look like just a symbol on a CAD   Let’s take digital-enabled automation
            by digitizing your processes.      drawing, but you should demand    the next step. Bending conduit can
                                               of your BIM software that the wall   constitute about 50 percent of your
            It is estimated that people spend   assembly incorporates fabrication   labor on any given job. And it’s one of
            30 percent of their working hours   intelligence, brand and part numbers,   your biggest areas of risk. In order to
            seeking information and context.   information about its construction   accomplish fast and reliable shop flow,
            (“What room and panel is this box   sequence, source panel, and more.  your BIM fabrication software should
            associated with?” “When is the                                       drive fabrication by:
            backordered material coming?”)     Having this information informs every   •  Accurately calculating the bend radii of
                                               succeeding activity in the workflow:  your various machines and shoes




                                                                 www.ieci.org | November/December 2021  | Insights Magazine  15