COMMERCIAL (ELECTRICAL CONTRACTS
               BETWEEN $1,500,001 AND $5,000,000)

























            BRET’S ELECTRIC




            RE-4 SCHOOLS                                                                                             IEC NATIONAL 2019 AWARDS  |  EXCELLENCE IN ELECTRICAL CONSTRUCTION





            Bret’s Electric was recognized for its work on the
            RE-4 Schools.
            Windsor RE-4 school district worked hard to get a bond
            project approved to improve the district. They recognized
            their aging buildings were in need of an energy efficient
            upgrade. Just over $4 million of the bond amount was
            accounted for the improvement of the electrical, fire
            alarm and technology systems within 242,000 square
            feet of 5 buildings: Mountain View Elementary, Tozer
            Elementary, Skyview Elementary, Windsor Middle School
            and the District Administration Building. Bret’s Electric
            was hand selected to be part of the GC/mechanical/
            electrical contractor team through a unique interview
            process that proved to be beneficial for the district.

            Bret’s Electric coordinated the trash dumpsters, de-lamping   positive impact on the summer work, but the spring
            and lamp recycling, metal scrap recycling, as well as floor   break work could not had been done without the help
            protection and ceiling tile removal/re-installation for   of a great partner and IEC member The Lighting Agency
            the ambitious week. We were scheduled for seven work   (TLA). Design schedules on this project were pushed
            days to complete the task but were able to exceed our   close to the spring break start date. While working with
            projections. Bret’s Electric completed the 1,028 light fixture   TLA, we were able to coordinate factory schedules to
            transformation in four and a half days, just under 1,900   commit to produce and deliver the 1,028 fixtures within a
            manhours. This jump on the schedule had an incredibly
                                                            two week timeframe, just before spring break started.











                                                         www.ieci.org  |  November/December 2019  |  Insights Magazine  25